Port of Oulu invests in efficiency
Over the past year, we have implemented significant improvements to our cargo handling capacity. The latest project – the widening of the shore ramp – was commissioned today 1st Dec 2025.
This upgrade enables cargo handling through three ramps on Enabler vessels instead of the previous two. Along with the 9-meter ramp extension, we also reinforced and expanded the quay area’s erosion protection, improving the long-term durability of the structures.
Western Quay Timber Storage Yard
During this past autumn, the port’s timber storage yard was expanded by 8,000 square meters to meet the growing demand for timber storage.
The expansion eases storage pressure and improves logistics efficiency. In the future, the yard is also planned to be paved, further increasing its usability.
Both projects were carried out by Kreate Oy – thank you for the excellent cooperation!
More information:
Infrastructure Manager Anssi Kemppainen / Tel. +358 50 379 6271
Cranes ready for growing container volumes!
The Port of Oulu’s new Crane 8 has been in operation for a few months, bringing significant efficiency and new capabilities to container handling.
Learn more about the crane’s construction phases and details here >>
At the same time, we have completed the electrical modernization of container crane 7, improving its energy efficiency and operational reliability.
More information:
Traffic Manager Sampo Kananen / Tel. +358 40 703 2751
Watch Youtube-video from constuction work >>